Easington Gas Storage Facility - 2500 Cable Ducts Sealed in 6 Weeks with CSD Rise Duct Seals

Easington Gas Storage Facility - 2500 Cable Ducts Sealed in 6 Weeks with CSD Rise Duct Seals

Client: Amec
Location: East Yorkshire Coast, UK
Date: 2008

CSD Duct Seals Project

The largest undersea pipeline in the world, the Langeled Pipeline, provides 20 per cent of Britain's gas supplies. The project consisted of sealing 2500 cable ducts with CSD Rise Duct Seal Kits in just six weeks before completion.

The gas receiving station based on the East Yorkshire coast, needed the 2500 cable entry ducts sealed to prevent gas and water ingress, and as cables entered buildings to provide fire protection too.

CSD was approached by Amec to survey the site and contracted a six week window to complete the cable sealing work. In order to do this CSD needed to supply a huge amount of material quickly and so the CSD factory and its Rise extrusion lines worked continuously for over one week. In addition CSD trained 18 of Amec's personnel to install the 2500 cable entry duct seals.

The CSD Rise material was supplied and the quick method of installation saw all 2500 cable ducts sealed well within the six week window, ensuring no delay on the Langeled project.

With the Rise cable sealing system, CSD provides a high performing gas and watertight seal tested to last in excess of 50 years, with the benefit of easily adding or removing cables at anytime in the future. The CSD Rise Duct Seal, which is included within the current WIMES specification, ensures compliance with the DSEAR regulations, even in misshapen, rectangular and vertical ducts, with a large volume of cables passing through.